Dear all,


with OE 16 we are build a Manufacturing Order which has several Sub Manufacturing orders :

MO001 depends on MO002 and MO003

Is there a way to plan MO0002 and MO003 when planning MO001


regards


Maurice

Avatar
Zrušiť
Autor Best Answer

Hi Lars,

many thanks for this input which clarify things for us

Indeed we can adjust the hierarchy of MO by manually linking the last operation of MO2 to the first of MO1 so that MO2 is made before MO1

The next step would be for Odoo folks to make this automatic when Planning MO1, system should plan all the sub MO

Many many thanks

Maurice