Hello Odoo Family-
Here's my situation:
I exclusively have MTO products.
My SO's run 30 to 40 lines, and therefore, I could have as many MOs. Each of MOs takes roughly 4/5 hours to produce.
I have sales and manufacturing security lead times that add up to 10 days.
I want to use the planning functionality and associated Gantt charts to make sure my shop floor team is organized.
Upon clicking Plan, Odoo only plans forward. Here's an example:
Delivery Date is 7/31.
MO/1 is planned for 7/21 @ 9am
MO/2 is planned for 7/21 @ 1pm
MO/3 is planned for 7/22 @ 9am
I have had a few cases where the planned work schedule for AFTER the delivery date.
My expectation is that it would go backward, so the last MO would be completed on 7/21.
Has anyone else experienced this? Did you do custom dev?
This one took me weeks to explain to Odoo support and I was finally told that this is a feature and not a bug.