This question has been flagged

Hello Odoo Family-

Here's my situation:

I exclusively have MTO products.

My SO's run 30 to 40 lines, and therefore, I could have as many MOs. Each of MOs takes roughly 4/5 hours to produce.

I have sales and manufacturing security lead times that add up to 10 days.

I want to use the planning functionality and associated Gantt charts to make sure my shop floor team is organized.

Upon clicking Plan, Odoo only plans forward. Here's an example:

Delivery Date is 7/31.

MO/1 is planned for 7/21 @ 9am

MO/2 is planned for 7/21 @ 1pm

MO/3 is planned for 7/22 @ 9am

I have had a few cases where the planned work schedule for AFTER the delivery date.

My expectation is that it would go backward, so the last MO would be completed on 7/21.

Has anyone else experienced this? Did you do custom dev?

This one took me weeks to explain to Odoo support and I was finally told that this is a feature and not a bug.